Tuesday, May 19, 2015
Fit tubing 6hrs
Bent the lower longeron, cut and fit all the diagonals for the second fuselage side. This has a reworked lower longeron that incorporates a fishmouth scarf stepdown. I will be matching the other side to this one.
Sunday, May 17, 2015
Fit tubing 3hrs
Cut and ground fishmouths on the lower diagonals up to the landing gear area. Still have to figure out the placement and transition from 7/8"- 3/4" tubing. It has an angle and changes tubing diameter.
Saturday, May 16, 2015
Fit tubing 4hrs
Mounted the vise to the table. Clamped the top longeron, and cut diagonals. Started to cut the fishmouths and fit them to the top.